Australian Strategic Materials (ASM) has released its Quarterly Activities Report for the period ending 30 June 2026.

“Our work during the Quarter was driven by three parallel objectives: progressing the Schemes with Energy Fuels, continued production ramp-up and expansion at the Korean Metals Plant (KMP), and progress of the Heap Leach Option pre-feasibility study (PFS) at the Dubbo Project”
Rowena Smith
Managing Director & CEO, ASM
Highlights
- Rare earth metal and alloy production continues to increase
The Korean Metals Plant (KMP) dispatched ~45 tonnes of NdFeB alloy and NdPr metal, with total production increasing for the second quarter in a row. - Facility expansion to 3,600tpa nameplate capacity
Installation of eight new furnaces at the KMP completed, progressing Phase 2 expansion activities. - Scaling-up heavy rare earth metal development
Commissioning of next-generation pilot-scale HRE metallisation furnace continued, supporting the development of terbium and dysprosium production. - MREP pathway offers simpler and lower cost route to production at Dubbo Project
Mixed rare earth precipitate (MREP) product pathway further examined to inform comprehensive Heap Leach Option pre-feasibility study.